NEW QUESTION 30
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.

  • A. SAP Concur
  • B. SAP Ariba
  • C. SAP C/4HANA
  • D. SAP Field glass
  • E. SAP SuccessFactors

Answer: A,B,D

 

NEW QUESTION 31
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.

  • A. Add the agreement to the source list and mark itfor MRP relevance.
  • B. Add the agreement to the quota arrangement and mark it for MRP relevance.
  • C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Answer: A,C

 

NEW QUESTION 32
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

  • A. The planning strategy is infinite.
  • B. The work center has several individual capacities.
  • C. The Change Planning Direct on indicator is set.
  • D. Alternative resources are fully occupied.

Answer: A,B

 

NEW QUESTION 33
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.

  • A. Continuous flow materials
  • B. Co-products
  • C. Waste products
  • D. By-products
  • E. Bulk materials

Answer: B,C,D

 

NEW QUESTION 34
If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?

  • A. Minimum wait time
  • B. Production time
  • C. Goods receipt processing time
  • D. Queue time

Answer: D

 

NEW QUESTION 35
What are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 3 correct answers to this question.

  • A. Assign the alert profile to the overall profile.
  • B. Create object selection variant for product-related alerts.
  • C. Create object selection variant for resource-related alerts
  • D. Create object selection variant for transportation lane-related alerts.
  • E. Assign the overall profile to the authorization profile.

Answer: A,B,C

 

NEW QUESTION 36
In your project,you have several materials that are planned by different people. How can you assign the planning responsibility?

  • A. MRP planning file
  • B. MRP controller
  • C. MRP group
  • D. MRP type

Answer: B

 

NEW QUESTION 37
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

  • A. Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
  • B. Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.
  • C. Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
  • D. Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator

Answer: B

 

NEW QUESTION 38
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.

  • A. In-house production time
  • B. Total replenishment lead time
  • C. Operation duration
  • D. Planned delivery time

Answer: A,D

 

NEW QUESTION 39
Where do you maintain the duration of a producton operation?

  • A. Material master
  • B. Routing
  • C. Bill of material (BOM)
  • D. Work instructions

Answer: B

 

NEW QUESTION 40
What does it mean for the production planner when MRP works with infinite capacities?

  • A. MRP creates capacity requirements only if the work center has sufficient capacity.
  • B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
  • C. MRP creates capacity requirements without checking the capacity of a work center.
  • D. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

Answer: C

 

NEW QUESTION 41
Which time elements are relevant for lead t me scheduling of a product on order? Note: There are 2 correct answers to this question.

  • A. Float after production
  • B. Setup time
  • C. Total replenishment lead time
  • D. Planned delivery time

Answer: A,D

 

NEW QUESTION 42
What are the consequences if operation status Dispatched is set for a production order operation?

  • A. You can reschedule the operation using lead the scheduling.
  • B. You canreschedule the order using material requirements planning.
  • C. You can reschedule the operation using finite Scheduling in a planning board.
  • D. You can reschedule the order using lead time scheduling.

Answer: C

 

NEW QUESTION 43
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?

  • A. Picking list
  • B. Transfer Order
  • C. Kanban
  • D. Backflushing

Answer: A

 

NEW QUESTION 44
What are the possible results of a production planning run inAdvanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

  • A. Scheduling agreement schedule line
  • B. Purchase requisition
  • C. Production order
  • D. Stock transport order
  • E. Planned order

Answer: A,B,E

 

NEW QUESTION 45
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

  • A. The planned order is converted to a production order.
  • B. The planned order generates capacity requirements.
  • C. The planned order's component availability is checked
  • D. The planned order's components are copied from the picking list.

Answer: B

 

NEW QUESTION 46
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A. To reduce the number of material masters
  • B. Tosimplify the structure of bills of material
  • C. To reduce the number of changes required in bills of material
  • D. To increase the number of planning levels
  • E. To make the assignment of components easier

Answer: B,C,E

 

NEW QUESTION 47
Your project team decides to use a make-to-order planning strategy for a strategic material in discretemanufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.

  • A. Sales order-specific planning run is required.
  • B. Sales order-specific stock is created
  • C. Production orders are created with sales order reference.
  • D. Storage location MRP areas are required.
  • E. Net requirements calculation is sales order-specific.

Answer: B,C,E

 

NEW QUESTION 48
......