Latest [Oct 17, 2022] Real SAP C_TS422_2020 Exam Dumps Questions [Q66-Q86]

Share

Latest [Oct 17, 2022] Real SAP C_TS422_2020 Exam Dumps Questions

C_TS422_2020 Dumps To Pass SAP Certified Application Associate Exam in One Day (Updated 150 Questions)

NEW QUESTION 66
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Work Center BOM
  • B. Functional Location BOM
  • C. Class BOM
  • D. Sales Order BOM

Answer: B,D

 

NEW QUESTION 67
You have a quality control check to avoid using a high-value component tin faulty materials in subsequent assembly operations. How do you account for potential scrap of the high-value material?

  • A. Enter the operation scrap and set the net indicator in the component of the bill of material of the assembly.
  • B. Enter the component scrap in the component of the bill of material of the assembly and leave the net indicator initial in the bill of material.
  • C. Enter the component scrap in the material master of the assembly and set the net indicator in the routing operation where V Dthe component is used
  • D. Enter the assembly scrap in the material master of the component and set the net indicator in the component of the bill of material of the assembly.

Answer: C

 

NEW QUESTION 68
What must be used in the system to plan the requirements for different subcontractors separately?

  • A. Production versions
  • B. Storage locations
  • C. Planning plant
  • D. MRP areas

Answer: D

 

NEW QUESTION 69
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?

  • A. Use the minimum order quantity.
  • B. Use the MRP type for vendor managed inventory.
  • C. Use the reorder point.
  • D. Use the fixed lot size procedure.

Answer: D

 

NEW QUESTION 70
What is the purpose of collective orders?

  • A. To manage production orders for an entirefinished product on multiple levels
  • B. To combine order management of co-products and by-products with the main product
  • C. To post production costs ona cost collector instead of the production order
  • D. To post any component withdrawals single back flush with order confirmation

Answer: A

 

NEW QUESTION 71
Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials? There are 2 correct answers to this question.

  • A. Storage location data
  • B. MRP area data
  • C. Production version data
  • D. Warehouse number data

Answer: A,D

 

NEW QUESTION 72
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?

  • A. Infinite resource and finite strategy
  • B. Finite resource and infinite strategy
  • C. Finite resource and finite strategy
  • D. Infinite resource and infinite strategy

Answer: C

 

NEW QUESTION 73
You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question.

  • A. Create and assign a new graphical object for setup time in the planning board.
  • B. Run setup minimization heuristics or optimizer.
  • C. Create and assign setup group/setup keys in the production data structure.
  • D. Create and assign a setup matrix with setup transition time to the resource

Answer: A,D

 

NEW QUESTION 74
What are some of the advantages of using Kanban? There are 2 correct answers to this question.

  • A. Replenishments are created close to the actual need
  • B. Replenishments are based on centralized planning
  • C. It is mostly accomplished by manual postings
  • D. It is a simplified form of production control

Answer: A,D

 

NEW QUESTION 75
Which of the following time elements does MRP use during backward scheduling for in-house production?
There are 2 correct answers to this question.

  • A. Planning time fence
  • B. Goods receipt processing time
  • C. Opening period
  • D. Planned delivery time

Answer: B,C

 

NEW QUESTION 76
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA.
When can you use mode selection?

  • A. When multiple operations are maintained for one product
  • B. When alternate resources are used within one operation
  • C. When multiple production versions are maintained for one product
  • D. When multiple planned orders exists in one resource

Answer: B

 

NEW QUESTION 77
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.

  • A. Individualconversion
  • B. Partial conversion
  • C. Full conversion
  • D. Order release

Answer: B,C

 

NEW QUESTION 78
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

  • A. It is converted into a planned order.
  • B. It is converted into a reservation.
  • C. It is converted into a production order.
  • D. It is converted into a schedule line.

Answer: B

 

NEW QUESTION 79
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers tothis question.

  • A. Documentation of quality data with Quality Management
  • B. Recipe approval (with Engineering Change Management)
  • C. Use of the GMP compliant flag in relevant master data applications
  • D. Predefined GMP compliant process order types to meet audit requirements
  • E. Use of the digital signature function to check and run business processes

Answer: A,B,E

 

NEW QUESTION 80
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

  • A. Demand Planning (DP)
  • B. Material Requirements Planning (MRP)
  • C. Capacity Requirements Planning (CRP)
  • D. Supply Network Planning (SNP)

Answer: B

 

NEW QUESTION 81
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

  • A. Creation of dependent requirements
  • B. Creation of a purchasing contract
  • C. Change of the storage bin
  • D. Creation of a sales order
  • E. Change of the material'sprocurement type

Answer: A,D,E

 

NEW QUESTION 82
In which data object is the production line (Repetitive manufacturing relevant work center) maintained?

  • A. Bil1 of material
  • B. Cost collector
  • C. Production version
  • D. Repetitive manufacturing profile

Answer: C

 

NEW QUESTION 83
What is a typical transportation processing SAP Transportation Management?

  • A. Transportation Planning, Order Management, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
  • B. Order Management, Transportation Planning, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
  • C. Transportation Planning, Transportation Execution, Order Management, Freight Costing and Settlement, Analytics and Reporting
  • D. Order Management, Transportation Planning, Freight Costing and Settlement, Transportation Execution, Analytics and Reporting

Answer: B

 

NEW QUESTION 84
For what production type are production orders used?

  • A. Period and quantity-oriented production
  • B. Process manufacturing processes
  • C. Discrete manufacturing processes
  • D. Replenishment controlled by control cycles

Answer: C

 

NEW QUESTION 85
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?

  • A. The plant-specific status
  • B. The cross-plant status
  • C. The most restrictive status
  • D. The least restrictive status

Answer: C

 

NEW QUESTION 86
......


SAP C_TS422_2020 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Introduction to SAP S/4HANA Production Planning < 8%

Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning.

Material Requirements Planning in SAP S/4HANA 8% - 12%

Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures.

Process Orders in SAP S/4HANA < 8%

Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP).

Demand Management in SAP S/4HANA < 8%

Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning.

Master Data in SAP S/4HANA > 12%

Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version.

Production Orders in SAP S/4HANA > 12%

Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation.



C_TS422_2020 Exam Certification Details:

Cut Score:56%
Duration:180 mins
Sample Questions: SAP C_TS422_2020 Exam Sample Question
Languages:English
Exam:80 questions

 

C_TS422_2020 Exam Brain Dumps - Study Notes and Theory: https://www.examstorrent.com/C_TS422_2020-exam-dumps-torrent.html

100% Guaranteed Results C_TS422_2020 Unlimited 150 Questions: https://drive.google.com/open?id=1V37Jtenr71Y1SleVxPWoVzAuqKdkPi1-