PRINCE2 methodology is a popular project management framework that has been widely adopted by organizations around the world. PRINCE2 stands for Projects IN Controlled Environments, and it provides a structured approach to project management that ensures projects are completed on time, within budget, and to the desired quality standards. The PRINCE2 Foundation certification is the entry-level qualification in the PRINCE2 certification path, and it is designed to certify individuals in the basic principles of the PRINCE2 methodology.
NEW QUESTION # 183
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
- A. Amend the Work Package
- B. Write an Exception Report
- C. Raise an off-specification
- D. Raise a request for change
Answer: C
Explanation:
Section: Volume A
NEW QUESTION # 184
Which is a purpose of the Managing a Stage Boundary process?
- A. Provide the Project Board with sufficient information for approving the next stage
- B. Approve the next Stage Plan
- C. Control the link between the Project Manager and the Team Manager(s)
- D. Review and close any risks and issues identified during the previous stage
Answer: A
NEW QUESTION # 185
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2 . Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
- A. Both 1 and 2 are true
- B. Only 2 is true
- C. Only 1 is true
- D. Neither 1 or 2 are true
Answer: D
NEW QUESTION # 186
Which management level should approve a course of action if project-level tolerance is exceeded?
- A. Project manager
- B. Corporate, programme management or the customer
- C. Project board
- D. Team manager
Answer: B
NEW QUESTION # 187
Which level of management sets the project level tolerances?
- A. Project manager
- B. Corporate, programme management or the customer
- C. Project board
- D. Team manager
Answer: A
Explanation:
Reference http://prince2.wiki/Manage_by_exception
NEW QUESTION # 188
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
- A. Both 1 and 2 are true
- B. Only 2 is true
- C. Only 1 is true
- D. Neither 1 or 2 are true
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 189
Which plan provides the Business Case with costs during the Initiating a Project process?
- A. Stage Plan
- B. Initiation Stage Plan
- C. Team Plan
- D. Project Plan
Answer: D
NEW QUESTION # 190
Which describes risk appetite?
- A. An organization's unique attitude towards risk-taking
- B. A common set of risk categories, risk scales and evaluation techniques
- C. The risks to the expected benefits
- D. The budget set aside for potential changesto the scope of the project
Answer: A
NEW QUESTION # 191
Which does the Executive need to ensure is in place before the project is initiated?
- A. The Project Plan has been approved
- B. All Work Packages are authorized
- C. The Project Initiation Documentation is complete
- D. An understanding of how the project will contribute to corporate objectives
Answer: D
NEW QUESTION # 192
Which is a recommended quality review team role?
- A. Project Manager
- B. Administrator
- C. Assurance
- D. Project Support
Answer: B
NEW QUESTION # 193
Which statement applies to Stage Plans?
- A. Always have the same duration as the Project Plan
- B. Are produced at the same time as the Project Initiation Documentation
- C. Provide a baseline against which the Project Board monitor overall progress
- D. Assist the Project Manager in the day-to-day running and control of the project
Answer: D
NEW QUESTION # 194
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Organization
- B. Quality
- C. Change
- D. Progress
Answer: D
Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-progress.php
NEW QUESTION # 195
Which is NOT one of the levels of plan recommended by PRINCE2?
- A. Stage Plan
- B. Benefits Review Plan
- C. Project Plan
- D. Team Plan
Answer: B
NEW QUESTION # 196
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
- A. Stage Plan
- B. Follow-on action recommendations
- C. Communication Management Strategy
- D. Quality Management Strategy
Answer: C
NEW QUESTION # 197
What is an off-specification?
- A. A major risk
- B. A new requirement
- C. A type of issue
- D. A quality tolerance
Answer: C
NEW QUESTION # 198
Which describes a risk effect?
- A. The uncertainty expressed as a negative or favourable occurrence
- B. The impact(s) on the project objectives should the threat or opportunity occur
- C. The issue which is affecting the project and has resulted in a risk
- D. The change in the statusof a risk in response to actions taken to control it
Answer: B
NEW QUESTION # 199
What should influence the Project Board's decision whether to delegate its Project
Assurance responsibilities?
- A. Having insufficient authority to perform the role
- B. The preference of the Project Manager
- C. The need to involve key stakeholders on the project management team
- D. Having insufficient time to perform the role
Answer: D
NEW QUESTION # 200
Which describes risk probability?
- A. Timeframe within which the risk may occur
- B. Probable effect on the project delivering its objectives
- C. A measure of the likelihood of the risk occurring
- D. Level of risks which the project can tolerate before escalating to the Project Board
Answer: C
NEW QUESTION # 201
......